Phase I

Orientation Meeting May 17
Stakeholder Kickoff Meetings Jun 1,2,3 (All Day)
I & A Presentation
to Task Force Jun 14 (5-9 PM)
to SAWS Jun 14
to Stakeholder Groups Jun 22,23,24 (All Day)
to Public Jun 24 (5-9 PM)
Phase II
Charrette (Two Weeks) Jul 19-30 (All Day)
Charrette Results Presentation to Task Force Aug 3 (5-9 PM)
Charrette Results Presentation to SAWS Aug 3
Phase II Consensus Plan Presentation
to Task Force Aug 17 (5-9 PM)
to SAWS Aug 17
to Stakeholder Groups Aug 24,25 (All Day)
to Public Aug 25 (5-9 PM)
Phase III
Present Preliminary Implementation Plan
to Task Force Nov 2 (5-9 PM)
to SAWS Nov 2
to Stakeholder Groups Nov 8,9 (All Day)
to Public Nov 9 (5-9 PM)
Final Presentation
to Task Force Nov 23 (5-9 PM)
to SAWS Nov 23
to Stakeholder Groups Dec 7,8,9 (All Day)
to Public Dec 8 or 9 (5-9 PM)